Guruluwana MHPP

Guruluwana Mini Hydro Power Project was commissioned in 2006 & it is fed by Kalu Ganga located in Ratnapura. The capacity of this power plant is 2.0 Mw.

Projects Details

Capacity

2.0 Mw

Design Flow

1758L/S

River Catchment

Kalu Ganga

Effective Catchment Area

6.5km2

Head

1014.6m

Channel Length

674.5m

Av. Plant Factor

38%

Penstock Length

860m

Commissioned

2006

Turbine Type

Pelton