Bogandana MHPP

Bogandana Mini Hydro Power Project was commissioned in 2009 & it is fed by Weli oya located in Badulla. The capacity of this power plant is 5.0 Mw.

Projects Details

Capacity

5.0 Mw

Design Flow

6.9 m3 / Sec

River Catchment

Weli oya

Effective Catchment Area

89kmĀ²

Head

92m

Channel Length

3928m

Av. Plant Factor

26%

Penstock Length

258m

Commissioned

2009

Turbine Type

Francis

View of the Project Field